Fixed Duration Tasks in Project 2007

posted April 11th, 2008 by Stephen Sanderlin
1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

Earlier today in the EPMFAQ Forums, there was a discussion concerning an issue in Project 2007 whereby the Duration on a Fixed Duration task is set to 0d if the Work on that task either rolled up or was set to 0h.

This is divergent behavior from Project 2003, and one that appears to be causing issues for a rapidly increasing number of users. Many of us within the community have been aware of this issue for quite some time, but there appear to be many people that are unfamiliar with this little conundrum, be they users, administrators, or consultants.

Here’s my response to the question:

The issue you are referring to manifests when the Work for the task is set to 0h, whether by rollup or entry. This results in the task’s Duration being set to 0d. This is true for all Task Types, including Fixed Duration.




Discuss this post on the EPMFAQ Blog Posts Forum.


Related Posts




The opinions expressed on this site by the authors and those providing comments are theirs alone, and do not reflect the opinions of the respective employers of the authors or any employee thereof. Our respective employers are not responsible for the accuracy of any of the information supplied by on this site.

Terms of Use | Privacy Policy | Publishers

All content on this website is covered by the
Creative Commons Attribution-Share Alike 3.0 United States License.
Theme ©2007 The Heckerped WordPress Theme created by JTk of Doc5 under the Creative Commons Attribution License.